HOW TO ORDER
PROCESS:
1
INQUIRY + BUDGET
Client Sends SWIF Inquiry
-
Inquiry Received
-
SWIF Contacts Client to Confirm Project Details
PROJECT ESTIMATE
+ Feasibility Assessment
+ Preliminary Plan Options
[ 1 WEEK ]
2
DESIGN DEVELOPMENT
Client Selects Engineering Path
-
A: SWIF Hires an Engineer
> Engineering Estimate Provided > Client Signs-off
-
B: Client Hires an Engineer
SWIF Coordinates with Engineer to Develop the Design
-
Confirm Loads and Building Capacity
-
Develop Typical Rack Configuration
-
Develop SWIF-to-Roof Connection Details
-
Confirm Module Requirements
PROJECT DESIGN
+ Project Quote
+ Rack Plan and Details
+ Engineering Calculations
+ List of Itemized Rack Components
[ 2-4 WEEKS ]
3
ENGINEERING + PERMIT
SWIF Coordinates with Engineer to Create the Permit Set
-
Finalize All Array Configurations
-
Confirm SWIF-to-Roof Connection Details
-
Get Approval from Module Manufacturer When Needed
PERMIT SET
+ Stamped Drawings
+ Stamped Engineering Calculations
[ 2 WEEKS ]
Heading 6
4
PERMIT APPLICATION
Permit Applied for by Others
-
Permit Set Submitted to Building Department and
Other Entities Required for Project Approval
-
SWIF and Engineer Respond to Plan Review Comments as Needed
PROJECT APPROVED FOR CONSTRUCTION
[ 2 WEEKS ]
DELIVERABLES
5
FINAL PRICING + ORDER
SWIF Finalizes Design and Order
-
Client Provides SWIF with the Approved Permit Set
-
SWIF Adjusts Rack Design and Layout per the Approved Permit Set
FINAL REVISIONS
+ Revised Project Quote
+ Updated List of Itemized Rack Components
[ 1 WEEK ]
Heading 6
6
FABRICATION + DELIVERY
SWIF Releases Project for Fabrication
-
Client Signs-off on Revised Quote
-
Deposit Received
SWIF RACKING SHIPPED TO JOB SITE
+ Delivery Documentation
+ Quality Assurance